Status Update on Smith Road: Weather permitting the finishing touches of the Smith Road FiberMat Project will be applied in the near future. Please keep in mind, a FiberMat project is a process. The process is as such: Beginning on August 13th, Smith Road is to be evaluated periodically by the contactor. This is to ensure that the road is bonding in the desired FiberMat condition, also known as curing. When the contractor is satisfied with the condition of the road, they will sweep the loose stone and gravel and apply the fog seal, finalizing the project. Halfmoon Township thanks all citizens for their patience and understanding in the matter.